Project Manager meeting and money back!
So we met with the Project Manager last week. Seems like a no-nonsense, get shit done type of bloke.
We ran through the window schedule to make sure that was ok to send off (most of the joinery is standard, but the big bastard 6.6m stacker isn't stock so they need time to make that).
Scraping of the site should be done this week, and PM reckons we'll have roof on and watertight before Xmas, which is awesome.
We also discovered we don't need the 8000l rainwater detention tank that was planned. So that's a credit on the build. Not sure how much but should be a fair few bucks. Nice to have numbers flowing this way for once.
Comments
Post a Comment